Cana Island Restoration Update Week Eleven – the weather continues to be a major factor. Mortar grinding keeper’s house brick and stone foundation complete. Tuck-pointing of keeper’s house brick and stone foundation complete. Lead abatement continues. Metal work on top (seam re-soldering) of the lantern cap started. (Photos of the lantern cap below - above the lantern room) Metal work on replicating original gutters started. Insulation started Roof repair and sheeting installation started. Cedar top shingling started. WPS completes meter install, removes overhead wiring, and energizes underground line. Inspected and passed.