Paving on McQueen Smith to AL6 will begin on June 2nd. This work - TopicsExpress



          

Paving on McQueen Smith to AL6 will begin on June 2nd. This work will be accomplished at night. They will be grinding during the first 3-5 days of the project. After grinding is complete, they will pave one lane at a time. Driveways and turnouts will be accomplished last. The entire project will take 2-3 weeks, depending on the weather. If you have any questions, please contact Engineering at 334.595.0550.
Posted on: Tue, 27 May 2014 14:00:00 +0000