Question No : 37 In your new project, you have to provide a critical deliverable within five months and do not have time to go through the Conduct Procurements process. You decide to sign a contract with a supplier with whom your company has done some work in the past. The risk you are accepting in this situation is: Choice 1 The ability of the supplier to deliver the goods Choice 2 Collusion between the supplier and your team Choice 3 Lack of proper scope definition Choice 4 Lack of a legally binding agreement #Stevbros #PMP #PMBOK #ProjectManagement #QuanLyDuAn