Signalling work progress Signalling Work progress at Main Line. •All Signals from Koyambedu to Alandur Platform have been installed and tested. •Synchronization Loops which helps the train to stop automatically at Stations has been installed in Stations like Koyambedu, CMBT, and Ashok Nagar Vadapalani etc. and tested. • Automatic Train Protection equipments have been installed over the mainline, and testing under progress. •Automatic Train Supervision, which automatically set the routes for movements of the trains is being installed and is being tested from Operational Control Center at Koyambedu. •Automatic Train Control Systems is under testing Signalling Works Progress at Depot. Signal Installation is in progress. A track circuit, which detects the position of the trains at the Depot, is under Installation. OCC Installation and Testing in progress.