This is everything crews will be doing to Mineral Point Rd & Junction Rd next week....Wow. 1) Excavation for structures in the Jug Handle 2) Excavation of South Junction Road 3) Storm sewer installation across Mineral Point Road just east of Commerce 4) Storm Sewer night work for Westbound Mineral Point Road at Target Driveway 5) Bridge/retaining wall construction around the new Jug Handle 6) Bridge/retaining wall construction in the northwest quadrant of the intersection 7) Boring and jacking a new storm pipe under USH 12/14, just north of Mineral Point Rd 8) Possible night work on South Junction Road Wednesday, Thursday and Friday nights (9PM - 6AM) 9) Traffic switch on Mineral Point Road anticipated on Friday
Posted on: Fri, 12 Jul 2013 11:43:24 +0000