Got a call to program a DSP for a job that the integrator couldnt handle. The call came from the manufacturers rep. Also got a call from the project superintendent that represented the general contractor almost begging me to just make it work cause the integrator couldnt handle it. Walked into find the rack in this condition and nothing actually wired to the DSP. Them the client asked for no major interruptions to the background music system. The integrator didnt even have any wallplates installed yet and didnt pull enough wires for some locations... Gotta love the blue tape, electrical tape wire bundles, and hanging wallplates.... The integrator is about to get an invoice!