The U.S. Nuclear Regulatory Commission clarified its role in - TopicsExpress



          

The U.S. Nuclear Regulatory Commission clarified its role in future activities, costs and policies surrounding the Crystal River area nuclear plant. NRC representatives held a public meeting Thursday night, following up on Duke Energy’s submission of its Post-Shutdown Decommissioning Activities Report (PSDAR). The purpose was to discuss and receive public comments on the report, which Duke submitted early last month. It includes a description of decommissioning activities, a schedule and a cost estimate. There are also details on environmental impacts, management of spent nuclear fuel and site restoration. While the NRC does not have to approve the PSDAR, it reviews the report to determine if it meets regulatory requirements. #CitrusCountyChronicle chronicleonline/content/public-concerned-about-future-nuclear-costs?pc=1
Posted on: Sat, 18 Jan 2014 18:00:01 +0000