Hi Planners, I have an activity(8h/d) with 1d duration and a - TopicsExpress



          

Hi Planners, I have an activity(8h/d) with 1d duration and a labor resource(default 8h/d) is assigned to it.Activity duration got dragged 1 more day and the actual duration is 2days after schedule update, Original Duration=1 Actual Duration =2 Budgeted Units =8h But Actual Unit is showing 8h instead of 16h(so im over riding actuals manually) *I have Checked the auto compute actuals and calculate costs from units in resource details. *Tried Recalculate assignments cost from tools menu nbut with no effect. Awaiting for your valuable suggestions.Thanks in advance