In 17 days, Apec reached 13%. That means 0.76% per day. Therefore, - TopicsExpress



          

In 17 days, Apec reached 13%. That means 0.76% per day. Therefore, the balance of 87% will be finished in 114 days. OMG! That is an unacceptable outcome. So, I sought the assistance of higher authorities. Sirs: 1. Please ask NEA to send 20 more restoration teams. They sent 7 w 3 more otw 2. Tell or text RSA to increase his restoration teams to 40 from 21. He committed 33 pero kulang. He has 10 inhouse w 11 subcontract. Together w NEA -- 40 + 30 = 70 3. Please ask Meralco to send 10. For a total of 80. 4. Please instruct NEA-APEC to balance the effort over the 18 LGUS, 8 still ZERO and the rest even Daraga is barely 5pct. His team on the ground is concentrating too much on Legazpi coz its profitable. Tiwi and Manito the producer of clean & cheap are totally out of their priority. Right now 10 or 50pct of the 21 are in Legazpi. There should be teams earmarked per LGU. * Two fixed teams for Bacacay, Malilipot, Sto Domingo, Manito, Tiwi, Jovellar, Pioduran, Malinao, and Albay West Coast Pantao = 20 teams *5 fixed for big towns cities like Polangui, Camalig, Guinobatan, Oas, Libon, Ligao, Tabaco = 35 teams *10 fixed teams each to Legazpi and Daraga. At the current effort, we will finish just before Christmas and given potential for slippages, even after it. So much for private efficiency. This is for action by the state.
Posted on: Sat, 02 Aug 2014 03:18:14 +0000

Trending Topics



Recently Viewed Topics




© 2015