#PRINCE2 Question of the day Which of the following statements on Managing a Stage Boundary process is not true? 1. It is predicated on dividing the project into management stages 2. It aims to enable the Project Board to be provided with sufficient information by the project manager. 3. It provides a means by which an exception process can be implemented. 4. It is always used towards the end of the final stage.