VOLTA REGION ALWAYS SUFFERS UNDER NDC The 45-kilometre road contract from Asikuman Junction to Agate in the Volta Region which is part of the Lot Two of the Eastern corridor roads is being executed by G.S. International Developer Gh Ltd with the Government of Ghana as the funding agency. The contract, awarded on September 29, 2011 and commenced on December 5, 2011, was expected to be completed within 24 months at a cost of GH¢105,777,580.31. However, physical progress of work as of November 30, 2014 stood at 26.59%, while the financial outlays as of November 30, 2014 was 30.25%, with the overall time spent on the project to date standing at 36 months...........Mahama chop the money. I rest my case