COUNTRY CLUB ROAD IMPROVEMENTS Construction Update, Week of March - TopicsExpress



          

COUNTRY CLUB ROAD IMPROVEMENTS Construction Update, Week of March 3, 2014 • Contractor continues to install new sanitary sewer line between Love Road to Doniphan. • Contractor working on the south half of box culvert at Montoya Main Lateral, expected to be completed this week. • Texas Gas contractor continues to install new gas main line between Ocotillo St and Charl Ann. • Contractor working on concrete pavement of the inbound lanes of Hunters Glen. Estimated to be completed by 3/8/13. • Contractor installing new conduit for illumination between bridge and Santa Teresita.
Posted on: Tue, 04 Mar 2014 19:18:02 +0000