How do u measure & compare the progress using primavera? Progress - TopicsExpress



          

How do u measure & compare the progress using primavera? Progress is measured primarily against the baseline. If the baseline has been loaded with cost and/or resources, earned value management can be used for this purpose. If not, progress is measured as variance to baseline dates. Planned Value (PV) = budget at Completion (BAC) x Planned % Complete Earned Value (EV) = budget at Completion (BAC) x Actual% Complete Actual Cost (AC) = No formula, What you’ve actually spent on the project Schedule Performance Index (SPl) =Earned Value (EV) / Planned Value (PV) Schedule Variance (SV) =Earned Value (EV) – Planned Value (PV) Cost Performance Index (CPI) =Earned Value (EV) / Actual Cost (AC) Cost Variance (CV) = Earned Value (EV) -Actual Cost (AC)
Posted on: Fri, 07 Jun 2013 07:34:17 +0000