Update on the Water Project - Last night at the monthly meeting - TopicsExpress



          

Update on the Water Project - Last night at the monthly meeting our contractor, David Uher, updated us on the project. It does involve several city departments and our plumber so coordination around others work schedule has been a factor. May 14th is the anticipated date when work will begin. We will have 5 outlets along the main lane into the garden making access to water much improved. We will continue to have the reservoir too. For gardeners on the north side of the lane, do not plant within the front 5-6 feet of your plot as a trench for the water pipe will be installed. South side gardens will not have any trenching done. Thank you for your patience on this needed project. Mary Lotten
Posted on: Wed, 07 May 2014 11:18:23 +0000